At DY MNG, we are privileged to work with a team of highly dedicated professionals who possess extensive industry-specific experience and a commitment to excellence. Our team members hold relevant certifications in their respective areas of expertise and work collaboratively to deliver top-notch services to our customers. The teams are led by Loh Eng Hong and Ng Kian Nam whom are both Directors in DY MNG.
Eng Hong, with a B.Eng (Mech) Hons Degree, has accumulated almost twenty years of in-depth experience in various areas such as project management, HVAC system design, process utility installation, cleanroom design and build, and electronic plant tool hook-up projects. With his vast knowledge and practical experience, he is an invaluable asset to the DY MNG team and a critical player in the company’s continued success.
On the other hand, Kian Nam is an extensively qualified professional with a B.Eng. (Mech) Hons Degree, MBA, and multiple ASHRAE certifications, including High-Performance Building Design Professional (HPBD), Healthcare Facility Design (HFDP), HVAC Designer (CHD), Certified Data Centre Professional (CDCP) and Vibration Analyst CAT III. With more than 15 years of experience in project supervision and management, servicing of air conditioning systems, and construction of cleanrooms, Nam has successfully executed and managed several world-class projects, including cleanroom systems for electronics and healthcare industries and HVAC systems for hotels and commercial complexes. His technical prowess and exceptional management skills are instrumental in our project delivery system and upholding our high-quality assurance standards.
Project Reference
Project Reference
Vat Manufacturing Malaysia, Batu Kawan
Sustio@Simmtech Sdn Bhd, Batu Kawan
TF AMD Microelectronics Sdn Bhd, Bayan Lepas
Optics Balzer Malaysia, Seberang Prai
Renesas Semiconductor (Malaysia) Sdn Bhd, Bayan Lepas
IJM Plot B, Penang Gelugor
Anggun Residences, Batu Kawan
Micron Memory Malaysia Sdn Bhd, Batu Kawan
Project List
Project List
YEAR 2024
Item |
Project Description |
Customer |
1 |
Design and Build Renovation Works At Labour Ward, Level 5 |
Sunway Medical Centre Penang Sdn Bhd
|
2 |
Design and Build Renovation Works At Digestive Health Unit For New Scope Room, Level 3
|
Sunway Medical Centre Penang Sdn Bhd |
3 |
WWTP New Scada Room For KM Plant |
Molnlycke Heath Care Sdn Bhd
|
4 |
Cadangan Pindaan dan Tambahan Kepada Kilang Sedia Ada Di Premis No.2468, Di Atas Lot 654, 685 Dan 10214, Solok Perusahaan 2, Mukim 1, Seberang Perai Tengah, Pulau Pinang.
|
South Island Garment Sdn Bhd |
5 |
Cadangan Membina Masjid 1 Tingkat Yang Terdiri Daripada: 1) Satu Blok Masjid 2) Dua Buah Minaret 3) Satu Blok Dewan Serbaguna 1 Tingkat 4) 1 Unit Substation Dan Rumah Sampah Di Atas Sebahagian Lot PT702 (Lot 716 PA 84341) Seksyen 1, Bandar Tanjong Pinang, Daerah Timur Laut, Pulau Pinang.
|
Dato’ Sri Meer Sadik Bin Habib Mohamed |
5 |
IFX KLM 3 – FAB 2.0 on Lot 12012, 12013 & 72953 Bandar Kulim, Daerah Kulim, Kedah
|
Infineon Technologies (Kulim) Sdn Bhd |
6 |
NSC for Design & Build for Mechanical Works, Electrical works and Fire Protection Works Package
|
Sustio@ Simmtech Sdn Bhd |
YEAR 2023
Item | Project Description | Customer |
---|---|---|
1 | Proposed 1 Block 24-Storey Hotel with 10-Storey podium for Commercial Lots and Carpark on Part of Lot 2570, Section 4, Butterworth, Seberang Prai Utara, Penang. (Phase 2) | STC Property Management Services Sdn Bhd |
2 | GROB 550T Millturn Machine Project | SAM Precision (M) Sdn Bhd |
3 | Cadangan Pembangunan 24 Tingkat & 19 Tingkat Yang Terdiri Daripada i) 1 Blok Pangsapuri Kos Sederhana (195 unit) Di Paras 8 Hingga 24, ii) 1 Blok Pangsapuri Perkhidmatan (60 Unit) Di Paras 8 Hingga 19, iii) 7 Tingkat Podium Mengandungi Kedai / Pejabat Di Paras 1 – 2 (37 Unit) Dan Kemudahan Masyarakat Di Paras 7 Serta Tempat Letak Kenderaan Di Paras 1, 3-6 Di Atas Lot-lot 71117 Dan 71118, Jalan Sultan Azlan Shah, Mukim 12, Daerah Barat Daya, Pulau Pinang. | Sunrise Manner Sdn Bhd |
4 | Intel KSM Apr’21 Capital Reset Progressive Build Upgrade for Existing Factory Lot 8, Jalan Hi-Tech 2/3 Kulim Hi-Tech Park, 09000 Kulim, Kedah. – Work Package WP01 – Mechanical Dry & Wet System Installation | Intel Products (M) Sdn Bhd |
5 | Intel KSM May’21 Capital Reset Progressive Build Upgrade for Existing Factory Lot 8, Jalan Hi-Tech 2/3 Kulim Hi-Tech Park, 09000 Kulim, Kedah. – Work Package WP03 – Mechanical Dry & Wet System Installation | Intel Products (M) Sdn Bhd |
6 | Intel PELICAN – F02A HVAC System Installation | Intel Technology Sdn Bhd |
7 | Intel PELICAN – Process Vacuum System Package F47 | Intel Technology Sdn Bhd |
8 | Cadangan Mendirikan 1 Blok Pangsapuri 35 Tingkat (496 Unit) Termasuk Kemudahan Masyarakat Dan 5 Tingkat Tempat Letak Kenderaan (Hakmilik Strata) | PE Development (Penang) Sdn Bhd |
9 | Permohonan Pindaan Kecil Kepada Sebuah Kilang Dan Gudang Setingkat Serta Pejabat 3 Tingkat Sedia Ada Di Atas PMT799 (PT5825), Jalan Cassia Selatan 3/11, Taman Perindustrian Batu Kawan, Mukim 13, Seberang Perai Selatan, Pulau Pinang. | Ineo Tech Sdn Bhd |
10 | Cadangan Pembangunan Yang Mengandungi:Yang Mengandungi: A) Bangunan Kilang 1-Tingkat B) Pejabat 2-TingkatTingkat C) 1 Bangunan Pencawang Letrik 2-Tingkat D) 2 Bangunan Pondok Penjaga 1-Tingkat E) Lintasan Berbumbung Dan Bangsal Menunggu Bas 1-Tingkat Di Atas Pelot 1A, Persiaran Cassia Selatan 6, Kawasan Perindustrian Batu Kawan, Mukim 13, Seberang Perai Selatan, Pulau Pinang. |
VAT Manufacturing Malaysia Sdn Bhd |
11 | Hook Up Package for Zone A – Electrical Services Installation | Sustio Sdn Bhd |
12 | Construct A Underground Water Tank Including Necessary Labour, Material, Tools and Equipment | ClassA Industrial (M) Sdn Bhd |
13 | Intel Pelican Project – Kawasan Perindustrian Bayan Lepas, Pulau Pinang. Letter of Award (LOA) For: Package F08C03 – PG12 Chilled Water Piping Works | Intel Technology Sdn Bhd |
14 | Intel Pelican Project – Kawasan Perindustrian Bayan Lepas, Pulau Pinang. Letter of Award (LOA) For: Package F08C04 – Data Center 2 Mechanical Works | Intel Technology Sdn Bhd |
15 | The Construction and Development of Hotel and Office on the Project Land held Under H.S (D) 19313, PT209 Seksyen 8, Bandar George Town, Daerah Timor Laut, Pulau Pinang for ACMV & BMS Services Installation. | Flex P5 Chiller Upgrading |
16 | To Supply & Install Centralized PCW System At Batu Berendam Free Trade Zone, 75350 Melaka. (P23004) | Texas Instruments Electronics Malaysia Sdn Bhd |
17 | (P23007) Cadangan Pindaan Dan Tambahan Kilang 1 Tingkat Dan Pejabat 2 Tingkat Kepada Kilang Sediada Di Atas Lot 70874, Jalan Hi-Tech 13, Seksyen 39, Zon Industri Fasa 3, Taman Perindustrian Hi-Tech Kulim, Bandar Kulim, Daerah Kulim, Kedah Darul Aman. | Messrs. Watlow Electric Malaysia Sdn Bhd |
18 | To Supply and Install New Cooling Tower At 2522, Lorong Perusahaan 4, Prai Free Trade Zone, Phase 1, 13600 Seberang Prai Tengah, Penang. | Micron Memory Tools Hook Up (P23006) |
YEAR 2022
Item | Project Description | Customer |
---|---|---|
1 | Proposed New Dining Area and Expansion Existing Prayer Room on Lot 12376 and Lot 12455, Plot 21A, Hilir Sungai Keluang 3, Taman Perindustrian Bayan Lepas Fasa 4, Mukim 12, Daerah Barat Daya, Pulau Pinang. | Plexus Manufacturing Sdn Bhd. |
2 | Relocate Tape & Reel Operation at B2 at Phase 3, Bayan Lepas FIZ, 11900 Bayan Lepas, Penang. | Renesas Electronics (Penang) Sdn Bhd |
3 | Proposed Internal Retrofitting Works To Existing Factory on Plot 574, Lorong Perusahaan Empat, Kawasan Perusahaan Perai, Mukim 1, Seberang Perai Tengah, Penang. | Optics Balzers Malaysia Sdn Bhd |
4 | Proposed Renovation and Conversion of Existing Production Area to Class 10K Cleanroom for Existing Factory at Plot 87, Lebuhraya Kampung Jawa, Kawasan Perindustrian Bayan Lepas, 11900 Bayan Lepas, Penang. | Plexus Manufacturing Sdn Bhd |
5 | Cadangan Membina Kampus Utama “Management Science University” (MSU) 26 Tingkat (Fasa 2) yang Mengandungi: 1 Blok Hospital Swasta 14 Tingkat, 1 Blok Asrama 13 Tingkat Dan 13 Tingkat Podium Tempat Letak Kereta Di No 4 (PT No 1108), Persiaran Olahraga, Seksyen 13, 40100 Shah Alam, Selangor | MSU Asset Sdn Bhd |
6 | KM1 Die Sort Project – WP09 HVAC Ductwork & Exhaust Package | Exyte Malaysia Sdn Bhd |
7 | KM1 Die Sort Project – WP16 OFA / PVAC Package | Exyte Malaysia Sdn Bhd |
8 | Cadangan Skim Pembangunan Bercampur a. 3 Blok Rumah Pangsa 28 Tingkat, 33 Tingkat dan 38 Tingkat Yang Mengandungi 560 Uit Kediaman, Pejabat Badan Pengurusan, Dewan Orang Ramai, TNB Dan Kemudahan Awan Dan 6 Tingkat Tempat Letak Kereta Di Atas Lot 30655, Seberang Perai Tengah, Pulau Pinang | Sunrise Manner Sdn Bhd |
9 | Cadangan Medirikan Satu Blok Kondominium 18 Tingkat (Jenis Hak Milik Strata) Di Atas Lot 55 & 56, Bandar Perai, Persiaran Sembilang, Seberang Perai Tengah | Messrs NB Tropics Development Sdn Bhd |
10 | Valeo Air Conditioning And Mechanical Ventilation Installation | Valeo Malaysia Sdn Bhd |
11 | Proposed Construction of 1 Block Hotel 13 Storey (160 Rooms) | Gayarena Sdn Bhd (Bahang Bay Hotel) |
12 | Project MRT 2: Package S204 For Station at Kuchai Lama and Taman Naga Emas | MRT Corporation Sdn Bhd |
13 | Cadangan Mendirikan Sebuah Kilang 4 Tingkat Kepada Kilang 2 Tingkat Sedia Ada No. 73-C, Lintang Bayan Lepas, Taman Perindustrian Bayan Lepas FTZ, di atas Lot 12147, Mukim 12, Daerah Barat Daya, Kawasan Perindustrian Bayan Lepas, Pulau Pinang. | Stratus Automation Sdn Bhd |
14 | Proposed 3 Storey Factory Building Expansion and 8 Storey Multistorey Carpark to Existing TF AMD Plant at Lot 70087 (Part of Lot 7482), Lot 5639 and Lot 5640, Lintang Kampung Jawa, Kawasan Perindustrian Bebas, Bayan Lepas, Fasa 3, Mukim 12, Pulau Pinang. | TF AMD Microelectronics (Penang) Sdn Bhd |
15 | Cadangan Membina 1 Unit Kilang Elektronik Setingkat Dengan Lantai Mezzanine di atas Lot 4489 & 4490, Jalan Hi-tech 2/5, Kulim Hi-tech Park, Mukim Bandar Kulim, Kedah Darul Aman. | Kulim Technology Park Corporation Sdn Bhd. |
16 | Renovation Works involve Clean Room Architectural Work, Air Conditioning and Filtration, Electrical Services, Process Utilities, Fire Sprinkle, Test and Commissioning. | QES Mechatronic Sdn Bhd |
17 | Cadangan pindaan dan tambahan kepada 2 unit kilang industri ringan jenis berkembar 2 tingkat sediada kepada bangunan kilang 3 tingkat di atas No 7, 9 Lintang Bayan Lepas 2, Lot 16104 dan Lot 16105, Taman Perindustrian Bayan Lepas, Fasa IV, Mukim 12, Daerah Barat Daya, Pulau Pinang | Mipox Malaysia Sdn Bhd. |
18 | Intel KM1 Warehouse Conversion – Work Package WP01 – Mechanical Dry | Intel Technology Sdn Bhd |
19 | MSU Medical Center Level 6 ICU Renovation Works | MSU Hospital |
20 | Proposed Renovation and Conversion of Existing Production Area to Class 100K Cleanroom for Existing Factory at Plot 88, Lebuhraya Kampung Jawa, Kawasan Perindustrian Bayan Lepas, 11900 Bayan Lepas, Penang. | Plexus Manufacturing (Riverside East) Sdn Bhd |
YEAR 2021
Item | Project Description | Customer |
---|---|---|
1 | Design and Build Class 10K Cleanroom Extension at Lot 70087 (Part of Lot 7482) Lot 5639 and Lot 5640, Lintang Kampung Jawa, Kawasan Perindustrian Bebas, Bayan Lepas Fasa 3, Mukim 12, D.B.D Pulau Pinang |
TF AMD Microelectronics (Penang) Sdn Bhd |
2 | Pentamaster MediQ Class 100K Clean Room Upgrading For Pentamaster Corporation Bhd | Peninsular HoHup Sdn Bhd c/o Pentamaster Corporation Berhad |
3 | Cadangan mendirikan sebuah kilang 4 tingkat kepada kilang 2 tingkat sedia ada No. 73-C, Lintang Bayan Lepas, Taman Perindustrian Bayan Lepas FTZ, di atas Lot 12147, Mukim 12, Daerah Barat Daya, Kawasan Perindustrian Bayan Lepas, Pulau Pinang |
Peninsular HoHup Sdn Bhd c/o Stratus Automation Sdn Bhd |
4 | Mechanical, Electrical, Cleanroom Architectural & Process Utility Services Installation for Proposed 3 Storey Factory Building Expansion and 8 Storey Multistorey Carpark to Existing TF AMD Plant at Lot 70087 (Part of Lot 7482), Lot 5639 and Lot 5640, Lintang Kampung Jawa, Kawasan Perindustrian Bebas, Bayan Lepas, Fasa 3, Mukim 12, Pulau Pinang |
TF AMD Microelectronics (Penang) Sdn Bhd |
5 | Cadangan Membina 1 Unit Kilang Elektronik Setingkat Dengan Lantai Mezzanine Di Atas Lot 4489 & 4490, Jalan Hi-Tech 2/5, Kulim Hi-Tech Park, Mukim Bandar Kulim, Kedah Darul Aman For Tetuan Kulim Technology Park Corporation Sdn Bhd |
Peninsular HoHup Sdn Bhd c/o Kulim Technology Park Corporation Sdn Bhd |
6 | Proposed New Dining Area and Expansion Existing Prayer Room on Lot 12376 and Lot 12455, Plot 21A, Hilir Sungai Keluang 3, Taman Perindustrian Bayan Lepas Fasa 4, Mukim 12, Daerah Barat Daya, Pulau Pinang. | Plexus Manufacturing Sdn Bhd |
7 | Renovation Works involve Clean Room Architectural Work, Air Conditioning and Filtration, Electrical Services, Process Utilities, Fire Sprinkle, Test and Commissioning. | QES Mechatronic Sdn Bhd |
8 | Relocate Tape & Reel Operation at B2 at Phase 3, Bayan Lepas FIZ, 11900 Bayan Lepas, Penang. | Renesas Electronics (Penang) Sdn Bhd |
9 | Proposed Internal Retrofitting Works To Existing Factory on Plot 574, Lorong Perusahaan Empat, Kawasan Perusahaan Perai, Mukim 1, Seberang Perai Tengah, Penang. | Optics Balzers Malaysia Sdn Bhd |
10 | Proposed Renovation and Conversion of Existing Production Area to Class 10K Cleanroom for Existing Factory at Plot 87, Lebuhraya Kampung Jawa, Kawasan Perindustrian Bayan Lepas, 11900 Bayan Lepas, Penang. | Plexus Manufacturing Sdn Bhd |
11 | Renovation and Conversion of Existing Production Area to Class 100K and Class 10K Clean Room for existing factory at Lot 15111 (Lot Lama 1240) & 3671 Mukim 12, D.B.D. di Halaman Kampung Jawa, Zon Perdagangan Bebas Bayan Lepas, Pulau Pinang. | Clarion Malaysia Sdn Bhd |
YEAR 2020
Item | Project Description | Customer |
---|---|---|
1 | Proposed 1 Block 24-Storey Hotel with 10-Storey podium for Commercial Lots and Carpark on Part of Lot 2570, Section 4, Butterworth, Seberang Prai Utara, Penang. (Phase 2) | IJM Construction Sdn Bhd c/o STC Property Management Services Sdn Bhd |
2 | Kellogg Jump Warehouse Expansion Project | Kelington Technologies Sdn Bhd c/o Kellogg Asia Products Sdn Bhd |
3 | Proposed Design and Build Package for Warehouse and Office Upgrading Project at No 11 Jalan UUI/15, Seksyen U1 Shah Alam, 40150 Selangor | AA Pharmacy Healthcare Sdn Bhd (Glenmarie Shah Alam) |
4 | Proposed Retrofitting Works for Existing 2 Storey Factory on Lot 13906, Mukim 12, Daerah Barat Daya, Taman Perindustrian Bayan Lepas, Fasa 4, Lintang Bayan Lepas, Pulau Pinang. (BPEN 2) | Bruker (M) Sdn Bhd |
5 | Proposed Retrofit Works for existing warehouse (B PEN3) for Messrs. Bruker (M) Sdn Bhd for ACMV, Electrical & Fire Fighting Works | Bruker (M) Sdn Bhd |
6 | Installation of N2 CDA SS316 Piping & SGP Piping with Insulation Work for Project Deionized Water & Waste Services for Infineon Tower at Melaka | Organo (Asia) Sdn Bhd c/o Infineon Technologies (Malaysia) Sdn Bhd, Melacca |
7 | Klinik Kesihatan Air Conditioning Installation at Jinjang & Sungai Buloh, Medan Maju Jaya, Tanglin, Jasin Melaka, Ampang and AU2 | Routinemate Builder Sdn Bhd |
8 | MRI Room Supply, Installation, Testing & Commissioning of Air Conditioning and Ventilation System at Hospital Raja Perempuan Naizab II and Hospital Sultanah Nur Zahirah | Mega Radiation Sdn Bhd |
YEAR 2019
Item | Project Description | Customer |
---|---|---|
1 | Renovation and Conversion of Existing Production Area to Class 10K Clean Room for Existing Factory at Plot 87, Lebuhraya Kampung Jawa, Kawasan Perindustrian Bayan Lepas, 11900 Penang | Plexus (Riverside) Manufacturing Sdn Bhd |
2 | Proposed Renovation and Convert Existing Production Area to Class 10K Clean Room (ASM Clean Room Extension) for Existing Factory at Plot 87, Lebuhraya Kampung Jawa, Kawasan Perindustrian 11900, Bayan Lepas, Penang |
Plexus (Riverside) Manufacturing Sdn Bhd |
3 | Construction of Main Building Works for Cadangan Pembangunan Automated Storage and Retrieval System (ASRS) untuk Matra 5 beserta Bangunan Sokongan dan kerja-kerja berkaitan di Pangkalan Udara TUDM, Gong Kedak, Daerah Besut, Terengganu Darul Iman |
Rimbaco Sdn Bhd c/o Tetuan Kementerian Pertahanan Malaysia |
4 | Expansion of Class 10K Clean Room | Renesas Electronics (Penang) Sdn Bhd |
5 | Level 2 Class 100K Clean Room Extension | TF AMD Microelectronics (Penang) Sdn Bhd |
YEAR 2018
Item | Project Description | Customer |
---|---|---|
1 | VRV system installation for PLC1 Office | Schenker Logistics (Malaysia) Sdn Bhd, Bayan Lepas |
2 | Metrology Class 1K clean room | Schott Glass (Malaysia) Sdn Bhd |
3 | Process utility, air conditioning and ventilation system works for Conversion of existing warehouse area to moulding area on plot 410 & cover walkway area from moudling area to assembly area on plot 411, Lorong Perindustrian 8B, Kawasan Perindustrian Prai |
JVG Bina Sdn Bhd c/o Valeo Malaysia CDA Sdn Bhd, Kawasan Perindustrian Prai |
4 | Mechanical, electrical and interior design work for renovation of new building | MSU Holding Sdn Bhd, Ipoh |
5 | Proposed retrofitting works for existing factory on plot 574 (part of level 1, level 2, level 3 & level 4), Lorong Perusahaan 4, Zon Perindustrian Bebas Perai, Mukim 1, Seberang Perai Tengah, Penang |
Optics Balzers Malaysia Sdn Bhd, Perai |
6 | Class 100K clean room for EMS Bukit Minyak | Peninsular HoHup Sdn Bhd c/o Engineered Medical Systems Malaysia Sdn Bhd |
7 | Cadangan Pindaan Kecil Ruang Dalaman Kepada Pejabat 2 Tingkat & Kilang Setingkat Tingkat Sedia Ada No 82-A, Di Atas Lot 14863 (Plot 82a), Lintang Bayan Lepas, Fasa 4, Mukim 12, DBD, Bayan Lepas |
Bruker (Malaysia) Sdn Bhd |
8 | Proposed Construction of Class 10K Clean Room at Level 2, Plexus Riverside East Building | Plexus (Riverside) Manufacturing Sdn Bhd |
9 | Stargate 0.12A Laser Room Construction | Schott Glass (M) Sdn Bhd |
YEAR 2017
Item | Project Description | Customer |
---|---|---|
1 | Class 10K clean room | TF AMD Microelectronics (Pg) Sdn Bhd, Bayan Lepas |
2 | Class 10K clean room | Kobe Precision Technology Sdn Bhd, Bayan Lepas |
3 | Smoke spill system retrofit | Kontron Asia Pacific Design Sdn Bhd, Prai |
4 | GMP Grad D clean room | THP Medical Sdn Bhd, Penang Science Park |
5 | SDAE BMW Mal Engine Test Cell | FEV Europe GmbH, Kulim |
6 | P3L1 & P5L3 class 100K clean room construction | Inari Technology Sdn Bhd, Bayan Lepas |
7 | Mechanical & electrical work for workshop renovation job at Wisma Academy | Iqor Network Technology Malaysia Sdn Bhd, Petaling Jaya |
8 | Air conditioning and mechanical ventilation system installation for U Café, MSU | MSU Holding Sdn Bhd, Shah Alam |
9 | VRV system installation work for Student Village, MSU | Aqua Construction Sdn Bhd c/o MSU Asset Sdn Bhd |
10 | Air conditioning and mechanical ventilation system installation for new plant | Morrisey Integrated Dynamics Sdn Bhd, Sungai Petani |
11 | Mechanical, electrical and interior design work for renovation of new building | MSU Holding Sdn Bhd, Sungai Petani |
12 | Propose To Install Air Conditioning and Cold Room#1, Renovation Works At Level 2, Xiao En Centre for Air Conditioning and mechanical Ventilation Works and To Install Air Conditioning and Cold Room#2 |
Academy Of Silent Mentor |
13 | To Supply Labour, Tools and Material to Install AHY c/w Hot Tapping, Valve, Thermometer, Outgoing Wiring, Ducting, Bracket, Piping, Hacking, Repair Ceiling and Make Goods/ Material | Island Hospital, Penang |
14 | Supply, Installation, testing & Commissioning of Air Conditioning and Ventilation System and Evaporative Air-Cooled Hybrid Chiller System | MSU Hospital, Shah Alam |
15 | Metro Hospital, Sungai Petani Air Conditioning and Mechanical Ventilation Works | Metro Kurnia Sdn Bhd |
YEAR 2016
Item | Project Description | Customer |
---|---|---|
1 | Air conditioning and mechanical ventilation system installation for GMP Grade D & Grade C cleanroom | Peritone Health Sdn Bhd, Kulim |
2 | Class 10K clean booth, Lay Down Yard | Organo (Asia) Sdn Bhd, Kulim |
3 | Process cooling water system upgrading and machine hook up | P1, Flextronics Technology (Pg) Sdn Bhd, Prai |
4 | GMP Grad C Laboratory (Clean room) | Lab Dom AVMM (Asia) Sdn Bhd, Kota Kinabalu |
5 | VRV system installation and hot water system retrofit for hotel room renovation | Oriental Hotel Penang, Georgetown |
6 | Mechanical & electrical system installation work for Class 100K clean room | Optics Blazers Malaysia Sdn Bhd, Prai |
7 | Laboratory office | Lab Dom AVMM (Asia) Sdn Bhd, Kota Kinabalu |
8 | Mechanical & electrical system installation work for Class 100K clean room extension | Optics Blazers Malaysia Sdn Bhd, Prai |
9 | Air conditioning and mechanical ventilation work for Cadangan Membina Kampus Utama Manangement Science University 26 Tingkat Yang Mengandungi: 1 Blok Hospital Swasta 14 Tingkat, 1 Blok Asrama 13 Tingkat Dan 13 Tingkat Podium Tempat Letak Kereta |
Aqua Construction Sdn Bhd c/o MSU Asset Sdn Bhd, Shah Alam |
10 | Air conditioning and mechanical ventilation work for Cadangan Pembangunan Yang Mengandungi Parcel 1 (Section 1) 1 Blok Hotel 13 Tingkat (160 Bilik) | Harmony Teamwork Construction Sdn Bhd c/o Gayarena Sdn Bhd, Teluk Bahang |
YEAR 2015
Item | Project Description | Customer |
---|---|---|
1 | Class 10K clean room construction | Riverside, Plexus Manufacturing Sdn Bhd, Bayan Lepas |
2 | Nippon Paint (OEM building) air conditioning system installation | Nippon Paint (M) Sdn Bhd, Shah Alam |
3 | Air conditioning and mechanical ventilation system, fire protection and electrical system installation for boutique hotel | Natline Crest (M) Sdn Bhd, Kuala Lumpur |
4 | PP15001 IFKM FAB2UPW; class 100K clean room and class 100 clean booth | Organo (Asia) Sdn Bhd, Kulim c/o Infineon Technologies (Kulim) Sdn Bhd |
5 | Backgrind class 10K clean room expansion and Die Bank new set up class 50K clean room | M Site, Carsem (M) Sdn Bhd, Ipoh |
6 | Mechanical & electrical system installation work for Cadangan Membina Sebuah Bangunan 8 Tingkat Yang Mengandungi Tempat Letak Kereta 7 Tingkat Dan Dewan Serbaguna Di Tingkat 7, Brickfield | Perisai Hijau Sdn Bhd c/o Dewan Bandaraya Kuala Lumpur |
7 | Mechanical & electrical system installation work for renovation to Kolej PTPL at Plaza Platinum Sentral, KL Sentral | MSU Holding Sdn Bhd, Kuala Lumpur |
8 | Mechanical & electrical system installation work for air cooled chiller installation and production oven hook up work | Telmar Network Technology Sdn Bhd, Bayan Lepas |
9 | Air conditioning and process utilities piping system installation for Proposed Renovation Work to Existing Factory at Penang Science Park, Bukit Minyak | Lipco Electrica Engineering c/o Nolato EMC Production Center Sdn Bhd |
10 | Air conditioning and mechanical ventilation system installation for Cadangan Membaikpulih Bangunan Terbengkalai kepada Hotel Jimat 6 Tingkat (20 Bilik) Di Georgetown | Harmony Teamwork Construction Sdn Bhd c/o Optimum Synergy Sdn Bhd |
YEAR 2014
Item | Project Description | Customer |
---|---|---|
1 | Air conditioning and mechanical ventilation system installation for third floor retrofit project | Tanjung Medical Sdn Bhd, Georgetown |
2 | Air conditioning and mechanical ventilation system installation for analytical laboratory | Wipro Unza (Malaysia) Sdn Bhd, Subang Jaya |
3 | Air conditioning and mechanical ventilation system installation for Dipping Plant (B1) | Sentinex Sdn Bhd, Kulim Hi- Tech Park |
4 | Air conditioning and mechanical ventilation system installation for iDCC Shah Alam | Muafakat Kekal Sdn Bhd, Shah Alam |
5 | Cooling tower refurbishment work | Advance Micro Devices Export Sdn Bhd, Bayan Lepas |
6 | New mechanical system installation at Southbay production | Riverside, Plexus Manufacturing Sdn Bhd, Bayan Lepas |
7 | Mechanical system (process chilled water & compressed dry air) hook up | Advance Micro Devices Export Sdn Bhd, Bayan Lepas |
8 | Hotel room renovation (VRV system installation) | Oriental Hotel Penang, Georgetown |
9 | Additional & alteration works for Tetra Lab Level 7 at Innoplex Motorola | Motorola Solution (M) Sdn Bhd, Bayan Lepas |
10 | Osram GSS office retrofit at EPF Tower, Georgetown | Osram Opto Semiconductors (M) Sdn Bhd, Bayan Lepas |
11 | Air conditioning system for restoration work and gallery space for Odeon Cinema, Penang Road, Georgetown | Amazing Globe Sdn Bhd, Georgetown |
12 | Air conditioning and mechanical ventilation system installation for operation theater and retrofit of existing AHU room | Metro Kurnia Sdn Bhd, Sungai Petani |
13 | Cooling tower replacement work | JPE, Jabil Circuit Sdn Bhd, Bayan Lepas |
14 | Air conditioning and mechanical ventilation system installation for Cadangan Mendirikan 1 Blok Bangunan Akademik 4 Tingkat For Upland School | I.S.P School Association, Batu Ferringi |
15 | Air conditioning and mechanical ventilation system installation for Pindaan dan Tambahan Bilik Kepada 1 Blok Institusi Pengajian | Inti International College Penang Sdn Bhd, Penang |
16 | Air conditioning and mechanical ventilation system installation for corporate office at Bayan City | Seal Incorporated Bhd, Bayan Baru |
17 | Air conditioning and mechanical ventilation system installation for Cadangan Untuk Pindaan Dalaman Kepada 1 Blok Kedia/Pejabat 13 Tingkat | Pembinaan Mazur Sdn Bhd, Pulau Tikus |
18 | Air conditioning and mechanical ventilation system installation for Cadangan Mindirikan 51 Unit Rumah Berkembar | Palmex Industries Sdn Bhd, Sungai Ara |
YEAR 2013
Item | Project Description | Customer |
---|---|---|
1 | ACSU installation and testing & commissioningResearch & product development lab, clean room, cold & hot room design and build | Wipro Unza (Malaysia) Sdn Bhd, Subang Jaya |
2 | Mechanical installation work for new SMT/HLA line set up | Seaside, Plexus Manufacturing Sdn Bhd, Bayan Lepas |
3 | Air conditioning and mechanical ventilation system installation for new building | Butterworth Paper Cups Sdn Bhd, Nibong Tebal |
4 | Mechanical installation work for NPI project | P2A, Flextronics Technology (Pg) Sdn Bhd, Bukit Minyak |
5 | Air cooled chiller replacement work | Swiss Garden Golf Resort and Spa Damai Laut, Lumut |
6 | Re-insulate existing chilled water piping | Swiss Garden Golf Resort and Spa Damai Laut, Lumut |
7 | VFD installation for cooling tower fan motor and condenser water pump motor | Queensbay Mall, Bayan Lepas |
8 | Air conditioning and mechanical ventilation system installation for KMPG office, Gurney Paragon | Eowon Designs Sdn Bhd, Penang |
9 | Air conditioning and mechanical ventilation system installation for Cadangan Membina Sebuah Kilang Dan Pejabat 3 Tingkat Di Kampung Jawa | BH Electronics Sdn Bhd, Bayan Lepas |
10 | Air cooled chiller and pumps replacement project for Pusat Simulator Pejuang TUDM, Pangkalan Udara TUDM | Pan Kinetics Sdn Bhd, Butterworth |
11 | Air conditioning and mechanical ventilation system installation for conversion car park level 5 to laboratory | Island Hospital, Penang |
12 | Air cooler installation work for Cadangan Mendirikan Sebuah Pasar Setingkat | Amasser Developer Sdn Bhd, Penang |
YEAR 2012
Item | Project Description | Customer |
---|---|---|
1 | ACSU installation and testing & commissioning | One World Block B, Fujasa Property Sdn Bhd, Bayan Baru |
2 | Air conditioning and mechanical ventilation, process utilities, and fire protection installation for new chamber room expansion project | P2A, Flextronics Technology (Pg) Sdn Bhd, Bukit Minyak |
3 | Mechanical & electrical package for clean room convert to SMT/HLA production | Seaside, Plexus Manufacturing Sdn Bhd, Bayan Lepas |
4 | Class 100K clean room design and build for packaging area | Topaz Evergreen Sdn Bhd, Seri Kembangan |
5 | Air conditioning and mechanical ventilation system installation for new building | Georgetown Baptist Church, Georgetown |
6 | Air conditioning and mechanical ventilation system installation for new building | Continental Automotive Components (M) Sdn Bhd, Prai |
7 | Mechanical & electrical system for main building renovation work | Kolej PTPL Penang |
8 | Mechanical & electrical system for test kitchen renovation work | Kolej PTPL Penang |
9 | Major rest room renovation work | PG2, Intel Technology Sdn Bhd, Penang |
10 | Brianwood chiller setup and installation | PG2, Intel Technology Sdn Bhd, Penang |
11 | Air conditioning and mechanical ventilation system installation | Tian Tian Restaurant, Butterworth |
12 | Air conditioning and mechanical ventilation system installation for Cadangan Membina 4 unit 3 Tingkat Rumah Sesebuah Di Jalan Lim Ah Chai | Pembinaan Perisai Hebat Sdn Bhd, Georgetown |
YEAR 2011
Item | Project Description | Customer |
---|---|---|
1 | ACSU, mechanical ventilation and lift lobby pressurization system installation | One World Block B, Fujasa Property Sdn Bhd, Bayan Baru |
2 | ACSU installation and testing & commissioning | Syarikat Welleseley Trading Sdn Bhd, Simpant Ampat |
3 | Air conditioning and mechanical ventilation (VRF system) and fire protection installation for renovation works for RIO & PGO | University Technology Petronas, Bandar Sri Iskandar |
4 | Air conditioning and mechanical ventilation, process utilities, fire protection and goods hoist installation for RIM project set-up plan | P3, Flextronics Technology (Pg) Sdn Bhd, Bukit Minyak |
5 | ACSU and mechanical ventilation installation | Stesen Penyelidikan RRIM, Lembaga Getah Kedah |
6 | ACSU installation for Cadangan Membina dan Menyaipkan Blok Penginapan Pegawai Untuk Sekolah Ikhtisas Tentera Udara (SITU) | Yan Gap Construction Sdn Bhd, Tanjung Bungah |
7 | Air conditioning and mechanical ventilation system installation for Block Administration | Management & Science University, Shah Alam |
8 | Top floor mechanical & electrical facilities remediation project | Jabil Global Service, Jabil Circuit Sdn Bhd, Bayan Lepas |
9 | Level 2 production floor burn in room design and build | Jabil Global Service, Jabil |
10 | Air conditioning and mechanical ventilation system installation for Cadangan Pindaan Dan Tambahan Kilang 2 Tingkat Sedia Ada | Benchmark Electronics (M) Sdn Bhd, Bayan Lepas |
YEAR 2010
Item | Project Description | Customer |
---|---|---|
1 | WCPU upgrade, replacement and related works | Continental Automotive Instruments (M) Sdn Bhd, Prai |
2 | Cleanroom design and build for Ultrasonic Area | Persys Surface Technology Sdn Bhd, Prai |
3 | Air conditioning and mechanical ventilation (multi split system) installation | PULAPO, Pulau Langkawi |
4 | Cisco process cooling water system design and build | My Habitat City Central, Aman City Hotel Sdn Bhd, Kuala Lumpur |
5 | ACSU and mechanical ventilation installation | One World Block D, Fujasa Property Sdn Bhd, Bayan Baru |
6 | Clean room air conditioning and mechanical ventilation system installation | Renal Laboratories Sdn Bhd, Techpark @ Enstek |
7 | BAS upgrade, replacement and related works | UiTM Permatang Pauh |
8 | Process chilled water system (water cooled chiller and associated equipment) installation | P2A, Flextronics Technology (Pg) Sdn Bhd, Bukit Minyak |
9 | ACSU installation for Cadangan Untuk Mendirikan Satu Unit Rumah Sesebuah Tiga Tingkat, Changkat Minden | Pembinaan Perisai Hebat Sdn Bhd, Penang |
10 | Air conditioning and mechanical ventilation system installation for Cadangan Membina Sebuah Rumah Banglo 3 Tingkat Beserta 2 Tingkat Attic, 1 Tingkat Tempat Meletak Kereta Separa Basemen | Fernline Construction Sdn Bhd, Shah Alam |
11 | Air conditioning and mechanical ventilation system installation for Block Great Hall | Management & Science University, Shah Alam |
12 | Air conditioning and mechanical ventilation system installation for Block Islamic Center | Management & Science University, Shah Alam |
YEAR 2009
Item | Project Description | Customer |
---|---|---|
1 | Process chilled water system (air cooled chiller and associated equipment) installation | P2, Flextronics Technology (Pg) Sdn Bhd, Bukit Minyak |
2 | LEV exhaust upgrading and related works | P5, Flextronics Technology (Pg) Sdn Bhd, Perai |
3 | Air conditioning and mechanical ventilation system installation | PULAPO, Pulau Langkawi |
4 | Cisco process cooling water system design and build | Jabil Global Service, Jabil Circuit Sdn Bhd, Bayan Lepas |
5 | Air conditioning and mechanical ventilation system installation for Block Academic & Block Library/Lab | Management & Science University, Shah Alam |
YEAR 2008
Item | Project Description | Customer |
---|---|---|
1 | CRAC unit installation and testing & commissioning | M3 & M4, First Solar Malaysia Sdn Bhd, Kulim |
2 | ACSU & ACPU installation and testing & commissioning | P2, Jabil Circuit Sdn Bhd, Bayan Lepas |
3 | Waste water treatment plant piping installation and testing & commissioning | Chung Yih Steel, Seberang Perai |
4 | P1B Extension project M&E coordination service | P1B, Jabil Circuit Sdn Bhd, Bayan Lepas |
5 | Class 1K clean room design and build | Jabil Global Service, Jabil Circuit Sdn Bhd, Bayan Lepas |
YEAR 2007
Item | Project Description | Customer |
---|---|---|
1 | ACSU, ACPU & mechanical ventilation installation and testing & commissioning | Nihon Canpack (M) Sdn Bhd, Batu Gajah |
2 | Jyoto Work – awarded as waste water treatment plant | Jyoto Work, Sungai Petani |
YEAR 2006
Item | Project Description | Customer |
---|---|---|
1 | ACSU & ACPU installation and testing & | PE7, LKT Manufacturing Sdn Bhd, Bayan Lepas |